Como elaborar un cronograma de obra valorizado
Citation preview
Curso Taller: Ms Project 2013 MODULO I: Planeamiento y Programacin
Consultor: B. Lenin Soto Gomez Correo: sgl_6768@hotmail.com
Taller 5: CRONOGRAMA VALORIZADO
1.- DATOS GENERALES DEL PROYECTO
INICIO DE PROYECTO: 02/03/2015
PLAZO CONTRACTUAL: 2 MESES
FIN DE PROYECTO: 02/05/2016
CALENDARIO: Estndar
JORNADA: 8h/d 48h/s 20d/mes
2.- PRESUPUESTO CON SU RESPECTIVO A.P.U
S10
1705001
001
Costo al 17/01/2014
Und. Metrado Precio S/. Parcial S/.
325,277.96
1,380.00
m2 500.00 2.76 1,380.00
12,043.40
m3 268.48 27.49 7,380.52
m3 198.24 2.44 483.71
m3 84.65 49.37 4,179.17
311,854.56
26,361.30
m3 124.86 153.29 19,139.79
m2 124.40 33.35 4,148.74
m3 16.85 182.36 3,072.77
285,493.26
118,148.35
kg 1,780.48 5.16 9,187.28
m2 968.48 20.67 20,018.48
m3 267.40 332.62 88,942.59
167,344.91
kg 2,824.50 5.16 14,574.42
m2 1,684.50 20.67 34,818.62
m3 472.45 249.66 117,951.87
Cliente MUNICIPALIDAD PROVINCIAL DE YAROWILCA
Lugar HUANUCO - YAROWILCA - CHAVINILLO
Presupuesto
Presupuesto CERCO PERIMETRICO - C.N. RAMON CASTILLA
Subpresupuesto ESTRUCTURAS
01.01 OBRAS PRELIMINARES
01.01.01 LIMPIEZA DEL TERRENO MANUAL
Item Descripcin
01 ESTRUCTURAS
01.02.02 ELIMINACION DE MATERIAL EXCEDENTE DM=1 km
01.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO
01.02 MOVIMIENTO DE TIERRAS
01.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS
01.03.01.01 CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA
01.03.01.02 ENCOFRADO DE SOBRECIMIENTO h=0.30 m
01.03 CONCRETO
01.03.01 CONCRETO SIMPLE
01.03.02.01 COLUMNAS
01.03.02.01.01 ACERO DE REFUERZO fy=4,200 kg/cm2
01.03.01.03 CONCRETO SOBRECIMIENTOS MEZCLA 1:8 + 25% P.M.
01.03.02 CONCRETO ARMADO
01.03.02.02 VIGAS
01.03.02.02.01 ACERO DE REFUERZO fy=4,200 kg/cm2
01.03.02.01.02 ENCOFRADO
01.03.02.01.03 CONCRETO COLUMNAS f'c=210 kg/cm2
Costo Directo 325,277.96
SON : TRESCIENTOS VEINTICINCO MIL DOSCIENTOS SETENTISIETE Y 96/100 NUEVOS SOLES
01.03.02.02.02 ENCOFRADO
01.03.02.02.03 CONCRETO VIGAS f'c=210 kg/cm2
Curso Taller: Ms Project 2013 MODULO I: Planeamiento y Programacin
Consultor: B. Lenin Soto Gomez Correo: sgl_6768@hotmail.com
3.- HOJA DE PROGRAMACION
Tp: (Duracion)
f: (nmero de cuadrillas * turno)
Und. Metrado Precio S/. Parcial S/. Rend. Tu Tp f f real
m2 500.00 2.76 1,380.00 40.00 12.50 3.00 4.17 4.00 4 peones
m3 268.48 27.49 7,380.52 4.00 67.12 8.50 7.90 8.00 8 peones
m3 198.24 2.44 483.71 625.00 0.32 0.50 0.63 1.00
m3 84.65 49.37 4,179.17 18.00 4.70 5.00 0.94 1.00 8 peones
m3 124.86 153.29 19,139.79 25.00 4.99 5.00 1.00 1.00
m2 124.40 33.35 4,148.74 14.40 8.64 2.00 4.32 4.00
m3 16.85 182.36 3,072.77 20.00 0.84 1.00 0.84 1.00
kg 1,780.48 5.16 9,187.28 240.00 7.42 4.00 1.85 2.00
m2 968.48 20.67 20,018.48 25.00 38.74 9.50 4.08 4.00
m3 267.40 332.62 88,942.59 12.00 22.28 5.50 4.05 4.00
kg 2,824.50 5.16 14,574.42 240.00 11.77 6.00 1.96 2.00
m2 1,684.50 20.67 34,818.62 25.00 67.38 8.50 7.93 8.00
m3 472.45 249.66 117,951.87 22.00 21.48 5.50 3.90 4.00
01.03.02.02.02 ENCOFRADO
01.03.02.02.03 CONCRETO VIGAS f'c=210 kg/cm2
01.03.02.01.03 CONCRETO COLUMNAS f'c=210 kg/cm2
01.03.02.02 VIGAS
01.03.02.02.01 ACERO DE REFUERZO fy=4,200 kg/cm2
01.03.02.01 COLUMNAS
01.03.02.01.01 ACERO DE REFUERZO fy=4,200 kg/cm2
01.03.02.01.02 ENCOFRADO
01.03.01.02 ENCOFRADO DE SOBRECIMIENTO h=0.30 m
01.03.01.03 CONCRETO SOBRECIMIENTOS MEZCLA 1:8 + 25% P.M.
01.03.02 CONCRETO ARMADO
01.03 CONCRETO
01.03.01 CONCRETO SIMPLE
01.03.01.01 CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA
01.02.01 EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS
01.02.02 ELIMINACION DE MATERIAL EXCEDENTE DM=1 km
01.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO
01.01 OBRAS PRELIMINARES
01.01.01 LIMPIEZA DEL TERRENO MANUAL
01.02 MOVIMIENTO DE TIERRAS
I tem Descripcin
01 ESTRUCTURAS
Curso Taller: Ms Project 2013 MODULO I: Planeamiento y Programacin
Consultor: B. Lenin Soto Gomez Correo: sgl_6768@hotmail.com
EDT - DIAGRAMA GANTT RUTA CRTICA
Curso Taller: Ms Project 2013 MODULO I: Planeamiento y Programacin
Consultor: B. Lenin Soto Gomez Correo: sgl_6768@hotmail.com
CRONOGRAMA VALORIZADO
Item Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8
01 3,116.59 4,341.48 4,227.86 18,679.08 39,124.68 54,610.58 109,250.06 91,927.64 325,277.97
01.01 1,380.00 1,380.00
01.01.01 1,380.00
01.02 1,736.59 4,341.48 4,227.86 1,737.46 12,043.39
01.02.01 1,736.59 4,341.48 1,302.44
01.02.02 483.71
01.02.03 2,925.42 1,253.75
01.03 16,941.62 39,124.68 54,610.58 109,250.06 91,927.64 311,854.58
01.03.01 5,741.94 16,509.41 4,109.96 26,361.31
01.03.01.01 5,741.94 13,397.85
01.03.01.02 3,111.56 1,037.19
01.03.01.03 3,072.77
01.03.02 11,199.68 22,615.27 50,500.62 109,250.06 91,927.64 285,493.27
01.03.02.01 11,199.68 11,684.45 38,664.39 56,599.83 118,148.35
01.03.02.01.01 8,038.87 1,148.41
01.03.02.01.02 3,160.81 10,536.04 6,321.63
01.03.02.01.03 32,342.76 56,599.83
01.03.02.02 10,930.82 11,836.23 52,650.23 91,927.64 167,344.92
01.03.02.02.01 10,930.82 3,643.61
01.03.02.02.02 8,192.62 20,481.54 6,144.46
01.03.02.02.03 32,168.69 85,783.18
Descripcin
ESTRUCTURAS
EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS
ELIMINACION DE MATERIAL EXCEDENTE DM=1 km
RELLENO COMPACTADO CON MATERIAL PROPIO
OBRAS PRELIMINARES
LIMPIEZA DEL TERRENO MANUAL
MOVIMIENTO DE TIERRAS
ACERO DE REFUERZO fy=4,200 kg/cm2
ENCOFRADO
ENCOFRADO DE SOBRECIMIENTO h=0.30 m
CONCRETO SOBRECIMIENTOS MEZCLA 1:8 + 25% P.M.
CONCRETO ARMADO
CONCRETO
CONCRETO SIMPLE
CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10
CEMENTO-HORMIGON 30% PIEDRA
TOTALMes 1 Mes 2
ENCOFRADO
CONCRETO VIGAS f'c=210 kg/cm2
CONCRETO COLUMNAS f'c=210 kg/cm2
VIGAS
ACERO DE REFUERZO fy=4,200 kg/cm2
COLUMNAS