    Construction Computer Software www.ccssa.com Cape Town: + 27 21 465 2637 Centurion + 27 12 643 0380

    Portugal +351 21 486 6440

    Introduo ao CANDY

    Construction Computer Software

    Bill of Quantities

    CCS Demonstration Job

    Item Description Qty/Unit Gross Rate Gross Amount

    SECTION 2: VENTILATION SHAFT

    SCHEDULE NO.1: FAN FOUNDATION

    EARTHWORKS

    A Clear and strip site 3,600m2 1.10 3,960.00

    B Excavate in bulk, Class A material anddispose within 2km freehaul distance

    7,200m3 11.00 79,200.00

    C Excavation in foundations ne 2m deep 750m3 9.75 7,312.50

    D Excavate for working space in Class A

    material and backfill and compact to95% mod. AASHTO.

    440m3 6.26 2,754.40

    E Excavate in class A material fortrenches and use for backfill, compact,and dispose of surplus material

    260m3 17.42 4,529.20

    F Extra over all excavations in Class Amaterial for Class B material

    210m3 91.14 19,139.40

    G Fill ing under floors and aroundfoundations in layers of 150mm,compacted to 95% mod AASHTO

    7,680m3 7.93 60,902.40

    H Overhaul 14,400

    m3.km

    0.56 8,064.00

    I Dewatering of excavations 1Sum

    Construction Computer SoftwareRailway Line

    Standard Barchart

    CCS Demonstration Job

    Printed 13:53:38 12 July 2002 Page 1 of 2

    Activity Description Durn Start Finish

    Current

    25May

    8 22June

    6 20July

    3 17 31August

    14 28Sep

    12 26October

    9 23November

    7 21Dec

    2001

    4 18January

    1 15February

    1 15 29March

    12April

    2002

    A220 ContractualA200 Award contract 1 18/05/2001 18/05/2001A190 Set up site 10 21/05/2001 01/06/2001

    A210 Tunnel at Ch 2200 - 3450A080 Construct west tunnel portal 45 04/06/2001 03/08/2001A160 Construct east tunnel portal 45 06/08/2001 12/10/2001A090 Drive tunnel 85 06/08/2001 07/12/2001

    A100 Line tunnel 85 20/08/2001 11/01/2002

    A250 StructuresA150 Build bridge A 90 04/06/2001 12/10/2001A170 Station buildings 140 04/06/2001 11/01/2002A180 Build bridge B 90 10/09/2001 08/02/2002

    A230 Linear operationsA260 PreparationA00 0 St ri p topsoi l Ch 0000 - 1400 20 04/06/2 001 29/0 6/2001A27 0 St ri p topsoi l Ch 1470 - 2000 8 02/07/2 001 11/0 7/2001A01 0 St ri p topsoi l Ch 8000 - 6950 15 12/07/2 001 01/0 8/2001A28 0 St ri p topsoi l Ch 6800 - 3500 47 02/08/2 001 12/1 0/2001A020 Drainage Ch 0000 - 1400 20 18/06/2001 13/07/2001A290 Drainage Ch 1470 - 2000 8 16/07/2001 25/07/2001A030 Drainage Ch 8000 - 6950 15 26/07/2001 15/08/2001A300 Drainage Ch 6800 - 3500 47 16/08/2001 26/10/2001A040 Fill Ch 0000 - 1400 20 02/07/2001 27/07/2001A310 Fill Ch 1470 - 2000 8 30/07/2001 08/08/2001A050 Fill Ch 8000 - 6950 15 09/08/2001 29/08/2001A320 Fill Ch 6800 - 3500 47 30/08/2001 09/11/2001A060 Sub Base Ch 0000 - 1400 20 16/07/2001 10/08/2001A330 Sub Base Ch 1470 - 2000 8 13/08/2001 22/08/2001A070 Sub Base Ch 8000 - 6950 15 23/08/2001 12/09/2001A340 Sub Base Ch 6800 - 3500 47 13/09/2001 23/11/2001

    Award contract

    Set up site

    080 Construct west tunnel portal

    A160 Construct east tunnel portal

    A090 Drive tunnel

    A100 Line tunnel

    150 Build bridge A

    170 Station buildings

    A180 Build bridge B

    0 00 St ri p to ps oi l Ch 0 00 0 - 1 40 0

    A270 Strip topsoil Ch 1470 - 2000

    A 010 S tr ip tops oi l C h 8000 - 6950

    A280 Strip topsoil Ch 6800 - 3500

    A0 20 Draina ge Ch 00 00 - 1400

    A290 Drainage Ch 1470 - 2000

    A030 Dr ai nage C h 8000 - 6950

    A300 Drainage Ch 6800 - 3500

    A040 Fill Ch 0000 - 1400

    A310 Fil l Ch 1470 - 2000

    A05 0 Fi ll C h 80 00 - 69 50

    A320 Fill Ch 6800 - 3500

    A0 60 Sub Base Ch 0 00 0 - 1 400

    A330 Sub Base Ch 1470 - 2000

    A0 70 S ub Ba se Ch 80 00 - 6 95 0

    A340 Sub Base Ch 6800 - 3500

    .

    CONSTRUCTIONCOMPUTERSOFTWARE

    Construction Computer Software CCS Demonstration Job incl IndirectCASHFLOW ANALYSIS SUMMARY. Code: 08 Name: Foreign Currency

    -70,000,000

    -60,000,000

    -50,000,000

    -40,000,000

    -30,000,000

    -20,000,000

    -10,000,000

    0

    10,000,000

    20,000,000

    30,000,000

    40,000,000

    50,000,000

    60,000,000

    70,000,000

    80,000,000

    90,000,000

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

    Months

    Value

    OutFlow

    Inflow

    CashFlow

    CONSTRUCTIONCOMPUTERSOFTWARE

    Construction Computer SoftwareRailway Line

    Time Chainage Report

    CCS Demonstration Job incl Indirect

    25

    May

    8

    22

    June

    6

    20

    July

    3

    17

    31

    August

    14

    28

    September

    12

    26

    October

    9

    23

    Nove

    mber

    714

    Dec

    2001

    18

    January

    1

    15

    February

    1

    15

    29

    March

    12

    26

    April

    10

    24

    May

    7

    21

    June

    2002

    0

    RaillinkEast

    1,4

    00

    BridgeA

    2,0

    00

    Eastportal

    3,5

    00

    Westportal

    5,8

    00

    Stationboundry

    6,2

    00

    Stationboundry

    6,8

    00

    BridgeB

    8,0

    00

    RaillinkWest

    trackstart

    ConstructEastportal C

    onstructWestportal

    Drive

    tunn

    el

    Line

    tunn

    el

    BuildbridgeA

    Stationbuildings B

    uildbridgeB

    StriptopsoilC

    h0000-1400

    Striptopsoil

    StriptopsoilCh8000-6950

    StriptopsoilCh6800-3500

    DrainageCh00

    00-1400

    DrainageCh8000-6950

    DrainageCh6800-3500

    FillCh0000-1

    400FillCh

    1470-2000

    FillCh8000-6950

    FillCh6800-3500

    SubBaseCh

    0000-1400

    SubBaseCh14

    70-2000

    SubBaseCh8000-6950

    SubBaseCh6800-3500

    Ballast Ch 0-2000

    Ballastthr

    utunnel20

    00-3500

    Ballastpasttunnel3500 -

    6800Lay track Ch 0 - 8000

    Handoverpro

    . !